Cisco Exam Questions

In the implement phase, which three tasks are associated with the activity to develop a project mana

In the implement phase, which three tasks are associated with the activity to develop a project management plan? (Choose three.)

A.
Define Technical Escalation procedures

B.
Establish project budget

C.
Define work Breakdown structure

D.
Present staging plan to customer

E.
Identify Risks and Risk Mitigation plans

F.
Define customer and partner stakeholders