You need to deploy FC-FC routing between two Gen 5 edge fabrics across an FCIP link.
Each edge fabric contains a single Brocade 6520 switch. Your backbone fabric consists of
two Brocade 7800 Extension Switches. How do you enable FC-FC routing using FCIP?

A.
Configure E_Ports between the 7800s and VE_Ports on each edge fabric connecting to
EX_Ports in the backbone.
B.
Configure VE_Ports between the 7800s and VE_Ports on each edge fabric connecting to
VEX_Ports in the backbone.
C.
Configure VEX_Ports between the 7800s and E_Ports on each edge fabric connecting to
EX_Ports in the backbone.
D.
Configure VE_Ports between the 7800s and E_Ports on each edge fabric connecting to
EX_Ports in the backbone.