Which of the following situations is characteristic of a make-to-stock environment?

A.
Customer involvement is typically very high.
B.
The master schedule is stated at the finished product level.
C.
The impact of technology on the production process will be large.
D.
Work in process (WIP) represents the largest cost of inventory.