Which of the following processes converts the master production schedule into resource requirements

Which of the following processes converts the master production schedule into resource
requirements that are then compared to the available resources?

A.
Rough-cut capacity planning

B.
Material requirements planning

C.
Capacity requirements planning

D.
Resource planning