What is the order point when demand is 120 units per week, the lead time is 2 weeks, and safety st seenagape 8 years ago What is the order point when demand is 120 units per week, the lead time is 2 weeks, and safety stock is 60 units? A. 360 B. 180 C. 240 D. 300 ← Previous question Next question →