After a quality improvement program has been successfully implemented, the greatest cost of control seenagape 8 years ago After a quality improvement program has been successfully implemented, the greatest cost of controlling quality typically is the cost of: A. inspection. B. prevention. C. appraisal. D. failure. ← Previous question Next question →