With respect to earned value analysis, which of the following is the value of work actually complete

With respect to earned value analysis, which of the following is the value of work actually completed?

A.
Actual Cost (AC)

B.
planed Value (PV)

C.
Cost Variance (CV)

D.
Earned Value (EV)