Who provides the inputs for the original estimates of activity durations for tasks on the project pl seenagape 9 years ago Who provides the inputs for the original estimates of activity durations for tasks onthe project plan? A.Project sponsor B.Project manager C.Person responsible for project scheduling D.Person who is most familiar with the task ← Previous question Next question →