Who is responsible for the project deliverables in this scenario?

[tagged]
Hans is the program manager for his organization. His current project has seven constituent projects that each will create deliverables for the organization. Who is responsible for the project deliverables in this scenario?

A.
Project managers

B.
Hans

C.
Program director

D.
Hans and each project manager