Who has the responsibility for informing the final deliverable to all stakeholders?

Who has the responsibility for informing the final deliverable to all stakeholders?

A.
Project Manager

B.
Sponsor

C.
Team Lead

D.
Management

Explanation:
Project Manager has the responsibility for informing the final deliverable to all stakeholders.