PMI Exam Questions

Which written document helps monitor who is responsible for resolving specific problems and concerns

Which written document helps monitor who is responsible for resolving specific problems and
concerns by a target date?

A.
Project Plan

B.
Responsibility Matrix

C.
Issue Log

D.
Scope Document