Which type of risk response is this? seenagape 12 years ago A part of a project deals with the hardware work. As a project manager, you have decided to hire acompany to deal with all hardware work on the project. Which type of risk response is this? A.Exploit B.Mitigation C.Transference D.Avoidance ← Previous question Next question →