PMI Exam Questions

Which type of risk response is this?

A part of a project deals with the hardware work. As a project manager, you have decided to hire a
company to deal with all hardware work on the project. Which type of risk response is this?

A.
Exploit

B.
Mitigation

C.
Transference

D.
Avoidance