Using values such as scope, cost, budget, and duration or measures of scale such as
size, weight, and complexity from a previous similar project as the basis for
estimating the same parameter or measurement for a current project describes
which type of estimating?

A.
Bottom-up
B.
Parametric
C.
Analogous
D.
Three-point