Which type of analysis is used as a general management technique within the Plan Procurements proces

Which type of analysis is used as a general management technique within the Plan Procurements
process?

A.
Risk assessment analysis

B.
Make or buy analysis

C.
Contract value analysis

D.
Cost impact analysis