PMI Exam Questions

Which tool or technique used in the Control Procurement…

Which tool or technique used in the Control Procurements process can be conducted during the execution of
the project to verify compliance with deliverables?

A.
Procurement documents

B.
Inspection and audits

C.
Estimate budget

D.
Risk register