Which tool or technique measures performance of the project as it moves from project initiation thro seenagape 9 years ago Which tool or technique measures performance of the project as it moves from project initiationthrough project closure? A.Resource leveling B.Parametric measuring C.Pareto chart D.Earned value ← Previous question Next question →