Which tool or technique measures performance of the project as it moves from project initiation thro seenagape 10 years ago Which tool or technique measures performance of the project as it moves from project initiationthrough project closure? A.Resource leveling B.Parametric measuring C.Pareto chart D.Earned value ← Previous question Next question →