PMI Exam Questions

Which schedule network analysis technique modifies the project schedule to account for limited resou

Which schedule network analysis technique modifies the project schedule to
account for limited resources?

A.
Human resource planning

B.
Fast tracking

C.
Critical chain method

D.
Rolling wave planning