Which schedule format usually shows both the project network logic and projects critical path schedu seenagape 12 years ago Which schedule format usually shows both the project network logic and projects critical path schedule activities with activity date information? A.Schedule Table B.Schedule network diagram C.Bar chart D.Milestone chart ← Previous question Next question →