Which schedule development technique modifies the project schedule to account for limited resources? seenagape 10 years ago Which schedule development technique modifies the project schedule to accountfor limited resources? A. Human resource planning B. Fast tracking C. Critical chain method D. Rolling wave planning ← Previous question Next question →