Which schedule compression technique has phases or activities done in parallel that would normally h admin 11 years ago Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially? A.Crashing B.Fast tracking C.Leads and lags adjustment D.Parallel task development ← Previous question Next question →