Which schedule compression technique has phases or activities done in parallel that would normally h seenagape 10 years ago Which schedule compression technique has phases or activities done in parallel thatwould normally have been done sequentially? A.Crashing B.Fast tracking C.Leads and lags adjustment D.Parallel task development ← Previous question Next question →