Which schedule compression technique has phases or acti… seenagape 8 years ago Which schedule compression technique has phases or activities done in parallel that would normally have beendone sequentially? A. Crashing B. Fast tracking C. Leads and lags adjustment D. Parallel task development ← Previous question Next question →