Which risk response is most likely to involve contingency reserves?

Which risk response is most likely to involve contingency reserves?

A.
Acceptance

B.
shaie

C.
Mitigate

D.
Transfer

Explanation:
Acceptance is when no change to the project is made for a risk. A contingency can be set aside to offset the impact of the risk.