Which risk response is appropriate for both positive and negative risk events? seenagape 12 years ago There are seven risks responses that a project manager can choose from. Which risk response isappropriate for both positive and negative risk events? A.Acceptance B.Sharing C.Transference D.Mitigation ← Previous question Next question →