You work as a project manager for BlueWell Inc. Your project is running late and you must
respond to the risk. Which risk response can you choose that will also cause you to update the
human resource management plan?

A.
Teaming agreements

B.
Transference

C.
Crashing the project

D.
Fast tracking the project