Which Project Time Management process includes bottom-u… seenagape 8 years ago Which Project Time Management process includes bottom-up estimating as a tool or technique? A. Estimate Activity Resources B. Sequence Activities C. Estimate Activity Durations D. Develop Schedule ← Previous question Next question →