which Project Time Management process? seenagape 8 years ago Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project TimeManagement process? A. Control Schedule B. Define Activities C. Develop Schedule D. Estimate Activity Resources ← Previous question Next question →