You are the project manger for Xylophone Phonics. This company produces children’s software programs that teach basic reading and math skills. You are ready to assign project roles, responsibilities, and reporting relationships. Which project Planning process are you working on?

A.
Human Resource Acquisition

B.
Acquire Staff

C.
Human Resource Planning

D.
Resource Planning

Explanation:
The Human Resource Planning process identifies project resources, documents roles and responsibilities of project team members, and documents reporting relationships.