You are the project manager of the GHY Project for your company. You need to complete a
project management process that will be on the lookout for new risks, changing risks, and risks
that are now outdated. Which project management process is responsible for these actions?

A.
Risk planning

B.
Risk identification

C.
Risk monitoring and controlling

D.
Risk analysis