Which project management plan will define who will be available to share information on the project

[tagged]
You work as the project manager for Bluewell Inc. Your project has several risks that will affect
several stakeholder requirements. Which project management plan will define who will be
available to share information on the project risks?

A.
Risk Management Plan

B.
Stakeholder management strategy

C.
Resource Management Plan

D.
Communications Management Plan