Which process uses occurrence probability and impact on… seenagape 8 years ago Which process uses occurrence probability and impact on project objectives to assess the priority of identifiedrisks? A. Identify Risks B. Perform Qualitative Risk Analysis C. Plan Risk Management D. Perform Quantitative Risk Analysis ← Previous question Next question →