Which process should be conducted from the project ince… seenagape 8 years ago Which process should be conducted from the project inception through completion? A. Monitor and Control Project Work B. Perform Quality Control C. Perform Integrated Change Control D. Monitor and Control Risks ← Previous question Next question →