Which process numerically analyzes the effect of identified risks on overall project objectives? seenagape 9 years ago Which process numerically analyzes the effect of identified risks on overall projectobjectives? A. Plan Risk Management B. Plan Risk Responses C. Perform Quantitative Risk Analysis D. Perform Qualitative Risk Analysis ← Previous question Next question →