PMI Exam Questions

which process might a project manager use risk reassessment as a tool and technique?

In which process might a project manager use risk reassessment as a tool and technique?

A.
Perform Qualitative Risk Analysis

B.
Monitor and Control Risk

C.
Monitor and Control Project Work

D.
Plan Risk Responses