PMI Exam Questions

Which process involves the creation of a document that provides the project manager with the authori

Which process involves the creation of a document that provides the project manager with the
authority to apply resources to a project?

A.
Define Activities

B.
Direct and Manage Project Work

C.
Develop Project Management Plan

D.
Develop Project Charter