Which process involves aggregating the estimated costs of the individual schedule activities or work

Which process involves aggregating the estimated costs of the individual schedule
activities or work packages?

A.
Estimate Costs

B.
Estimate Activity Resources

C.
Control Costs

D.
Determine Budget