Which process includes prioritizing risks for subsequent further analysis or action by
assessing and combining their probability of occurrence and impact?

A.
Perform Qualitative Risk Analysis
B.
Perform Quantitative Risk Analysis
C.
Plan Risk Management
D.
Plan Risk Responses
Attention Aiotesking,I have just bumped into your website and looked at PMP practice question with interest of signing up. Kindly help me get my account accessing. Despite a good try, your system is not taking my password reset request. This is a rich repository of training knowledge i cannot afford to miss out.