PMI Exam Questions

Which process in Project Time Management includes reserve analysis as a tool or technique?

Which process in Project Time Management includes reserve analysis as a tool or technique?

A.
Estimate Activity Resources

B.
Sequence Activities

C.
Estimate Activity Durations

D.
Develop Schedule