Which process in Project Time Management includes reserve analysis as a tool or technique? seenagape 9 years ago Which process in Project Time Management includes reserve analysis as a tool ortechnique? A. Estimate Activity Resources B. Sequence Activities C. Estimate Activity Durations D. Develop Schedule ← Previous question Next question →