PMI Exam Questions

Which process identifies whether the needs of a project can best be met by acquiring products, servi

Which process identifies whether the needs of a project can best be met by acquiring products,
services, or results outside of the organization?

A.
Plan Procurement Management

B.
Control Procurements

C.
Collect Requirements

D.
Plan Cost Management