Which process group is for detailed resource assignments and responsibilities?

Which process group is for detailed resource assignments and responsibilities?

A.
Human resources management plan

B.
Project charter

C.
Aplan

D.
Project management plan

Explanation:
Develop Human Resource Plan: Planning, identifying, documenting, and assigning project roles, responsibilities, and reporting relationships to individuals or groups.