Which Process Group includes the Manage Stakeholder Engagement process? seenagape 9 years ago Which Process Group includes the Manage Stakeholder Engagement process? A.Executing B.Planning C.Monitoring and Controlling D.Initiating Explanation:Reason: Control Stateholder Engagement is in the Monitoring and Control Process. ← Previous question Next question →