Which Process Group includes the Manage Stakeholder Eng… seenagape 8 years ago Which Process Group includes the Manage Stakeholder Engagement process? A. Executing B. Planning C. Monitoring and Controlling D. Initiating Explanation:Reason: Control Stateholder Engagement is in the Monitoring and Control Process. ← Previous question Next question →