Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate

Which Plan Schedule Management tool or technique may involve choosing strategic
options to estimate and schedule the project?

A.
Facilitation techniques

B.
Expert judgment

C.
Analytical techniques

D.
Variance analysis