PMI Exam Questions

Which output of Project Cost Management consists of quantitative assessments of the probable costs r

Which output of Project Cost Management consists of quantitative assessments of
the probable costs required to complete project work?

A.
Activity cost estimates

B.
Earned value management

C.
Cost management plan

D.
Cost baseline