Which one of the following is NOT an output of the process?

[tagged]
There are five outputs of the risk monitoring and controlling process. Which one of the following is
NOT an output of the process?

A.
Organizational process assetsupdates

B.
Risk register updates

C.
Vendor contracts

D.
Change requests