Which one of the following is not an output of the Define Activities process?

The Define Activities process is the first process in the project time management knowledge are a.
The Define Activities process creates just three outputs as a result of decomposition, rolling wave
planning, templates, and expert judgment. Which one of the following is not an output of the
Define Activities process?

A.
Activity list

B.
Milestone list

C.
Activity attributes

D.
Project document updates

Explanation:
Project document updates are not an output of the Define Activities process. Project document
updates are the outputs for estimate activity resources. Project document updates include the
following:
Activity list
Activity attributes
Resource calendars
Answer option A is incorrect. The activity list is an output of the define activities process.
Answer option C is incorrect. The activity attributes is an output of the define activities process.
Answer option B is incorrect. The milestone list is an output of the define activities process.