You work as a project manager for BlueWell Inc. You are preparing for the risk identification
process. You will need to involve several of the project’s key stakeholders to help you identify and
communicate the identified risk events. You will also need several documents to help you and the
stakeholders identify the risk events. Which one of the following is NOT a document that will help
you identify and communicate risks within the project?
A.
Risk register
B.
Activity cost estimates
C.
Stakeholder register
D.
Activity duration estimates