Mark works as a project manager for TechSoft Inc. Mark, the project team, and the key project
stakeholders have completed a round of qualitative risk analysis. He needs to update the risk
register with his findings so that he can communicate the risk results to the project stakeholders -including management. Mark will need to update all of the following information except for which
one?

A.
Prioritized list of quantified risks

B.
Watchlist of low-priority risks

C.
Trends in qualitative risk analysis

D.
Risks grouped by categories